Construction on Highway 60 from the junction of Highway 14 east of Eagle Lake to the City of Elysian has been progressing well, according to officials at the Minnesota Department of Transportation. Construction on this first phase began on April 15 and is expected to be complete by July 16. The detour consists of Highway 14 and Waseca County Road 3.

Starting July 16, construction will move to Phase 2 and will take place on Highway 60 from the City of Elysian to the junction with Highway 13 at Waterville. Traffic will be detoured to Highway 13 in Waterville, Le Sueur County Road 12 (Tetonka Lake Road), Le Sueur County Road 11 and Highway 60. Construction is expected to be complete in October.